Saturday, November 30, 2024
TWO IMPORTANT MEETINGS
Friday, November 29, 2024
Newsflash update
29/11/2024
Foyer
Wednesday, November 27, 2024
Show and Tell
WHAT IS GOING TO HAPPEN TO MY APARTMENT?
Wish lists
Tuesday, November 26, 2024
SITE PLAN
SITE PLAN FOR HERBERT GARDENS PROJECT
Sunday, November 24, 2024
Scaffolding
Saturday, November 23, 2024
Another glimpse into the past
Thursday, November 21, 2024
WEATHER TIGHTNESS
Tuesday, November 19, 2024
Decisions
Monday, November 18, 2024
WHY IS HERBERT GARDENS BUILT OF CONCRETE?
HG Newsflash 18 November
New
Zealanders are remarkable people. They were among the first in the world to use
concrete in construction; the lighthouse on Burgess Island, built in 1882, was
a pioneering use of pre-cast blocks. At the same time, pioneer engineers were
experimenting with reinforcing concrete – the Sacred Heart Cathedral in
Wellington, built 1895, is an example of this.
After that,
reinforced concrete really took off. It has many advantages. It is fire-resistant, looks good once clad,
and if well designed, it can withstand earthquake movement, because of its
inherent strength. It has much better sound-proofing than other materials. It transfers heat and cold more slowly, too,
reducing the need for high-maintenance air-conditioning. So, by the late 1920s, concrete was the choice
for building everything from bridges to public buildings that were as much as
three stories high.
In 1964,
when Herbert Gardens was designed by Biggs, Power and Clark, and built by P.
Graham and Sons, using reinforced concrete for a high rise building was still a
novelty. People used to gather on the Terrace during office lunch hours, to
watch the building grow. Unusually for that time, too, it was a slab and core
construction, where the floor/ceiling slabs were built around a core. It was a method that did not become common
until the 1980s.
It is not
an easy process. There was much research, into old photos and news reports as
well as architectural drawings, and on-site tests had to be carried out. Then the
job had to be analysed in detail, with many drawings made. It is extremely
important to know exactly where the reinforcing has landed after all these
years of creep. Meetings for workshopping have been frequent. And when the job
starts, it will involve a lot of testing, and a lot of drilling. And drilling
means a lot of vibration, which can shake off masonry dust and ceiling plaster –
plaster that may have asbestos in the mix.
But it will
be worth it, to return Herbert Gardens to the grand lady that aroused such
interest and admiration back in the mid-1960s.
Thursday, November 14, 2024
NEWSFLASH November 14, 2024:
Meetings:
There was yet another meeting at TBIG on
Wednesday afternoon, following the Board meeting on Tuesday night. The major topic was how asbestos-containing
ceilings will be handled, with a number of options that were discussed in
detail. This is part of getting ready for the foyer meeting on Monday 18th,
at 6pm. There is a lot to be discussed,
and I am certain there will be many questions to be answered. We need to
collect all the information possible, as time is getting short. The AGM is on 9 December, remember, part of
the pre-Christmas rush. All shareholders
will have papers to study about two weeks before that. And please be ready to fill in a proxy form
if you are not able to be present.
Moving in and out of your apartment:
There will be a timetable for this, which
Aoraki and TBIG are working on. A significant number of apartments will have to
be completely emptied, and so Damien has been negotiating with a number of
moving companies. Other apartments will have to have the furniture taken out of
rooms that are being worked on, and stored in other rooms. The movers could do this too, or individual
residents could manage it themselves.
What is going to make it easier is that
Aoraki have offered the use of their hoist to get furniture in and out of the
building, which will save the pressure on our poor old elevators.
This hoist will be set up at the bottom of
the steps by the back door, where the spare bins are stacked now. It will lead
up to the window in the third bedroom of the B apartments, which has to be
taken out and replaced by a fire spandrel, plus a new window and a panel. Not
only is this part of getting the fire rating of the building up to code, but while that part of the wall is open it
forms a handy access to the inside of the building for the workmen and their
materials.
| Image supplied by Marc Woodbury of Studio Pacific |
The website is https://www.govt.nz/browse/housing-and-property/insulation-and-energy-efficiency/paying-for-home-insulation/
Tuesday, November 12, 2024
NEWSFLASH November 12, 2024:
Elevators:
The constant failing of one or more of the
lifts is at the forefront of all our minds. So, hurrah, and thanks to the hard work of the
Otis team, both lifts are working as of today.
Long may that last, but fingers tightly crossed by all, the elevators
being so senior. Damien and I are still
having meetings with elevator representatives and engineers. Next week, we hope to be able to ride in one
or more new elevators in other apartment buildings, and meantime will be
studying the fine print in the quotes and contracts.
Meetings:
A meeting at TBIG
this morning and another to follow this afternoon, plus a Board meeting
tonight. Getting ready for the foyer
meeting next week. Talk was again about ACM removal or encapsulation, with the
option of gib ceilings over the encapsulated ceiling plaster. There is still a lot to be decided, and as
you are all aware, time is getting short.
The AGM is on 9 December, remember, part of the pre-Christmas rush. All shareholders will have papers to study
about two weeks before that.
Fire and Ventilation:
I did find out something interesting. Apartments D share a ventilation shaft in the kitchen. So that is why I can smell delicious dinners cooking in other levels of the building. These outlets to the ventilation shaft have to be remediated according to the latest code. So what will happen is that where the outlet is covered by a range hood, the range hood will be taken down, the hole to the shaft remediated, and then the range hood put back. The kitchen will look the same as it always did, with the assurance that it is now more fire-safe.
This, of course, depends on whether a range hood is there or not. In some D apartments the cooking hob has been moved to another side, and shelving or cabinets cover the outlet to the ventilation shaft. They will have to be moved, and then put back. Nothing can be guaranteed until the workmen come into the apartment and assess the situation.
Sunday, November 10, 2024
CHRISTABEL GIBSON
More on the test on 6C
So, data is being gathered, and incorporated in the scope of work. This has of course let to many meetings. It is going to be a very busy week with lots of workshopping, but we are getting there.
Friday, November 8, 2024
NEWSFLASH November 8, 2024:
Elevators:
The constant failing of one or more of the
lifts is at the forefront of all our minds.
Our elevators have done sterling work over the years, but we have to
remember that they are over 60 years old. Machinery parts are obsolete, and
cannot be replaced. Instead, the Otis
team are making up their own parts, in very difficult circumstances. Murray came to see Brigid and me last week,
while Damien was away with Covid, and he and Ben Budd had a positive programme
in mind. This morning Damien and I will
had a meeting with the Schindler rep, to gain ideas from a second company, as
part of a rigorous process of deciding what to do. Obviously, we are all
working hard to get a fixing for the problem underway as soon as possible.
And Otis maintainers are optimistic that we will have two lifts operating over the weekend.
Meetings:
As I have already revealed, on Tuesday
morning there was a 90-minute meeting at the TBIG offices, with good news from
Manus of Spectrum, who confirmed that the blockwork in level 12 does not need
more strengthening than in the rest of the levels.
On Tuesday evening the Board met with
Martin of TBIG and Jurgen of Quintons, to talk about costing and timing. Both
were very clear and helpful, and we are so grateful that they had agreed to
come along. The timing of the “vacations” of the various levels (when
apartments have to be vacated) is now a good approximate, but still open to
amendment.
This is complicated by the fact that
drilling at one level cannot happen until any ACM is dealt with on the level
below. This is because the drilling
could loosen ACM in an untreated ceiling. So a leapfrog version is being
discussed. It is estimated that ACM
treatment will take 10 days, but this is very flexible. Some levels have very
little work to be done, which would send the workers down two more levels
earlier than expected. A “cascade”
effect would follow in the timing, so that work might be done more quickly than
estimated, or maybe take longer. Very soon more precise time lines will be
calculated and can be presented in a logical fashion to you all.
Lots more to come, with new developments by
the hour. As they used to say in the old
days, keep tuned to this station!
And have a wonderful weekend.
Thursday, November 7, 2024
Windage
In the last HGNewsflash I mentioned the effect of wind force on the building, and asked for instances of creaking. The answers were interesting. No creaks, but rattling windows, particularly in the kitchens of A apartments.
I found out for certain that I am not qualified to navigate a container ship!
Tuesday, November 5, 2024
NEWSFLASH November 5, 2024:
Elevators:
The Otis team are still working hard for
us. Yesterday there was issue after issue with the northern lift. They now have to make up a steel plate at
their workshop to seal off a drum brake that has seized up and is leaking oil.
It is no wonder that elevator engineers are marine engineers, as that is a
constant worry at sea, too.
And no, the picture is not of their current premises. It is the building at 187 Vivian Street where they started in 1930. The photo was taken in 1978 and is in the Wellington Library collection.
Meetings:
This morning there was a 90-minute meeting
at the TBIG offices, with a great deal to discuss. First, good news from Manus of Spectrum, who
confirmed that the problems with level 12 that they were investigating turned
out to be no problem at all. Marc of Studio Pacific asked if any allowance had
been made for windage – wind movement in a storm. Manus said he would
check. Has anyone noticed their level creak,
though maybe only a little, during a gale?
This just shows how careful everyone is
being.
Which takes me to something else – a theory
for why the ACM people prefer to remove asbestos, rather than encapsulate and
encase. It could be because with encapsulation they have to be more careful! Not
just of embedded wiring and light fittings, but of wallpaper and furniture,
too, perhaps. An interesting thought!
We talked about the test in apartment
6C. As I saw, the reinforcing rod is
across the top and down the righthand side. I was told that every third row of
blocks was reinforced with concrete, too, which had to be chipped away. The
test team did well, leaving a very tidy scene.
Skip:
One person has asked about the skip, as it
is full. If there is more demand for it, another can be ordered.
Disks:
If the evacuation disk is missing in your
apartment, please tell Damien so he can get a replacement. This is essential in emergencies, as it lets
the Fire Wardens know that everyone has come down.
Tonight there is a Board meeting, with
Martin (TBIG) and Jurgen (Quintons).
More to report tomorrow.
Sunday, November 3, 2024
NEWSFLASH November 3, 2024:
Friday, November 1, 2024
Another glimpse into the history of 186 the Terrace
The party!!
I forgot to take photos! (But hopefully someone else memorialised the Welcome Home Party, and will forward the pix to druettjo@gmail.com) ...
-
To All Residents and Shareholders A nasty strain of flu is going around, and unfortunately it has felled Damien, Brigid, Opie, Lido. This m...
-
Welcome a New Director! At yesterday's Board meeting we had the great pleasure of voting in Geoff Fougere as a fellow director. He ha...
-
Ken Geard will be farewelled this Thursday 2pm at the Harbour City Funeral Home in Lower Hutt - across from the Hutt Hospital. All welcome...

















.jpg)